Temecula VCP Project |
|
Project Description: Total quantity pipe utilized: 3000’ 24’’ - 5000’ 15”
24” depth avg. 30’-31’ deep 15” depth avg. 20’ deep Slope on 24” .0010 Slope on 15” .0015 Prior to digging trench for 24” the area was excavated 50’ wide and 12’ deep with a Komatsu PC600. The balance was dug with a 48” bucket. 15” pipe was dug with a 36” bucket. All pipe was a rock encasement. Location: Temecula, CA Engineers/Contractors Involved: Design Engineer: Rick Engineering Contractor: Double D Pipeline Date of Completion: 14 Weeks
|